Moreland Dixon Culvert Replacement (Moreland Dixon Road)

The Moreland Dixon Culvert is located on Moreland Dixon Road at the north end of Collins Lake approximately 1.5km East of Perth Road. The existing multiplate culvert has a width of 2.8m, a height of 2.0m and a length of 32m. It is also located at a depth of 5.5m to the bottom of the pipe.

The existing culvert has experienced structural failure and is believed to have been installed prior to the 1990’s when Moreland Dixon Road was last reconstructed.

This culvert is currently in a stable condition and has required ongoing maintenance since March when the failure was first observed.

Work currently includes:

  • Excavation to expose the existing structure
  • Demolition of the existing structure
  • Installation of a new 2.4m diameter polymer laminated corrugated steel pipe
  • Backfill of new culvert
  • Reinstatement of pavement and installation of new guiderails

This replacement will offer a life expectancy of 50 years and aligns with the recommendations within the Asset Management Plan.

This project is categorized as “Exempt” under the 2024 Municipal Class Environmental Assessment process and is considered a pre-approved construction project under the Ontario Environmental Assessment Act.

Further information on the selected contractor and start dates will be provided on this web page. Notices will also be issued to properties in immediate proximity of the project.

The Moreland Dixon Culvert is located on Moreland Dixon Road at the north end of Collins Lake approximately 1.5km East of Perth Road. The existing multiplate culvert has a width of 2.8m, a height of 2.0m and a length of 32m. It is also located at a depth of 5.5m to the bottom of the pipe.

The existing culvert has experienced structural failure and is believed to have been installed prior to the 1990’s when Moreland Dixon Road was last reconstructed.

This culvert is currently in a stable condition and has required ongoing maintenance since March when the failure was first observed.

Work currently includes:

  • Excavation to expose the existing structure
  • Demolition of the existing structure
  • Installation of a new 2.4m diameter polymer laminated corrugated steel pipe
  • Backfill of new culvert
  • Reinstatement of pavement and installation of new guiderails

This replacement will offer a life expectancy of 50 years and aligns with the recommendations within the Asset Management Plan.

This project is categorized as “Exempt” under the 2024 Municipal Class Environmental Assessment process and is considered a pre-approved construction project under the Ontario Environmental Assessment Act.

Further information on the selected contractor and start dates will be provided on this web page. Notices will also be issued to properties in immediate proximity of the project.

  • Update: September 15, 2026

    UPDATE – September 15, 2026

    Works forecasted – week of September 21 to September 25

    • Contractor mobilization
    • Signage and detour route setup
    • Installation of environmental protection
    • Installation of dewatering devices
    • Removal of guiderail and asphalt

    Works forecasted – weeks of September 28 to October 2 (weather permitting)

    • FULL CLOSURE OF MORELAND DIXON ROAD AT CULVERT
    • Excavation for culvert replacement including support of existing utilities
    • Installation of new 32m long 2400mm diameter CSP culvert
    • Culvert backfill
    • New guiderail installation
    • Culvert cut paving
    • REOPEN ROADWAY TO TRAFFIC

    Works forecasted – weeks of October 2 to October 9th (weather permitting)

    • Remaining works such as topsoil, seed and line paint

    UPDATE – September 15, 2026

    Works forecasted – week of September 21 to September 25

    • Contractor mobilization
    • Signage and detour route setup
    • Installation of environmental protection
    • Installation of dewatering devices
    • Removal of guiderail and asphalt

    Works forecasted – weeks of September 28 to October 2 (weather permitting)

    • FULL CLOSURE OF MORELAND DIXON ROAD AT CULVERT
    • Excavation for culvert replacement including support of existing utilities
    • Installation of new 32m long 2400mm diameter CSP culvert
    • Culvert backfill
    • New guiderail installation
    • Culvert cut paving
    • REOPEN ROADWAY TO TRAFFIC

    Works forecasted – weeks of October 2 to October 9th (weather permitting)

    • Remaining works such as topsoil, seed and line paint
Page last updated: 15 Sep 2026, 01:50 PM