Update: September 15, 2026

UPDATE – September 15, 2026

Works forecasted – week of September 21 to September 25

  • Contractor mobilization
  • Signage and detour route setup
  • Installation of environmental protection
  • Installation of dewatering devices
  • Removal of guiderail and asphalt

Works forecasted – weeks of September 28 to October 2 (weather permitting)

  • FULL CLOSURE OF MORELAND DIXON ROAD AT CULVERT
  • Excavation for culvert replacement including support of existing utilities
  • Installation of new 32m long 2400mm diameter CSP culvert
  • Culvert backfill
  • New guiderail installation
  • Culvert cut paving
  • REOPEN ROADWAY TO TRAFFIC

Works forecasted – weeks of October 2 to October 9th (weather permitting)

  • Remaining works such as topsoil, seed and line paint