FAQs
When will construction start?
Replacement of the structure is expected to start in September 2026 with works continuing until October 30, 2026.
Who will complete the work?
The reconstruction project has been awarded to Crains Construction.
What is the project budget and where did the funding come from?
The overall budget for the project will be $770,500.
How is this going to affect traffic in the area?
There will be ongoing alternating single lane traffic for the majority of the project. Due to the depth of the excavation required, there will be a approximate 5-day road closure with detours in place during this critical stage of work. Details on the detour and timing of the road closure will be publicly advertised in advance.
How does this project consider fish, wildlife and species at risk?
The culvert replacement work will include components of in-water work however mitigation efforts will be included in the project to protect the waterway and shoreline environment. Consultations with the Conservation Authority and other agencies will provide direction on project timing, water restrictions, and measures to be included in the work area to protect the environment.
Will the construction work interfere with garbage or recycling collection?
Residents will continue to place garbage and recycling out for collection at end of their entranceway by 7am on the regular collection day, as required under the bylaw.
What will the hours of work be on the project?
Unless approved otherwise by the Township, hours of Construction will be set by By-Law 2015-41 - To Prohibit and Regulate Noise Within the Township of South Frontenac. Hours of construction on this project will typically be Monday to Friday from 7am to 7pm.
Weekend work may only be considered late in the project if weather delays are encountered. If weekend work is deemed necessary, advance notice will be provided to the area so that residents may plan accordingly.
What do I do if I live on the road near the project and have key events or activities (moving, family gathering, weddings, pool installations, site construction, etc..) planned this summer?
Residents are encouraged to reach out to the Township in advance to advise of any special events or activities that may be happening at their property this summer. Township crews will do their best to plan or schedule works in a manner that reduces inconveniences where possible.
This type of request can be made by contacting Public Services at 613-376-3027 or email pwsupport@southfrontenac.net.
How do I stay informed on this project as it progresses?
Residents near the work zone and surrounding areas are encouraged to subscribe or follow this project online to stay up to date on the progress.
Other options include reaching out by phone or email with contact information for your property. This will help the Township keep you informed as the project continues. Email addresses can be used to push information updates to residents; however individual addresses will not be shared for any other purpose.
Where can I find out more information on the project?
For further information on the project please contact the Public Services Department at 613-376-3027 or email pwsupport@southfrontenac.net with the subject line “Moreland Dixon Culvert Replacement”.