April 2021

Phase 1: Project Initiation

Building off public engagement which occurred in late 2019, the project was reinitiated in Spring 2021.

July → August 2021

Phase 2: Consultation on Policy Directions

Summer 2021

May → June 2022

Phase 3: Consultation on Draft Official Plan

Spring 2022

May → July 2022

Phase 4: Council direction to circulate the draft Official Plan to Indigenous Communities and external agencies for review

Fall 2022

September → October 2022

Phase 5: Circulate draft Official Plan to Indigenous Communities and external agencies for review

November → December 2022

Phase 6: Review & Incorporate Comments received from Indigenous Communities and external agencies

February → March 2023

Phase 7: Introduce Official Plan project to new Council, present the 2nd draft of the Official Plan to Council

April → May 2023

Phase 8: Consultation with Committees & Boards

April 25 → May 31 2023

Phase 9: Public Consultation – Statutory Open Houses

July → August 2023

Phase 10: Preparation of Final draft of Official Plan for Council

September 2023

Phase 11: Council provide direction to staff to schedule Statutory Open House and formal Public Hearing

October 2023

Phase 12: Statutory Public Meeting

November 2023

Phase 13: Adoption of the new Official Plan by South Frontenac Council