August 26, 2026

UPDATE – August 26, 2026

Works completed – weeks August 7 to August 21

  • Installation of retaining walls concurrent with backfill of structure
  • Placement of new concrete distribution slab including reinforcing steel on top of rigid frame structure
  • Installation of guide rail
  • Removal of cofferdam and environmental controls



Works forecasted – weeks of August 24 to September 10 (weather permitting)

  • Placement of hot rubberized asphalt waterproofing and protection board
  • Placement of hot mix asphalt
  • Line painting
  • Placement of guide rail on structure

Opening of structure to traffic