Round Lake Road Reconstruction (Duff Rd. to Latimer Rd.)

The Township of South Frontenac will be reconstructing the 2.0km section of Round Lake Road from Duff Road to Latimer Road during the summer of 2026. Round Lake Road was selected as a priority project for 2026 due to the poor road surface ratings identified within the Township’s 2022 Comprehensive Road Needs Study. The pavement condition ratings for the roadway were 40 (Poor) in 2025. Ongoing increases in unplanned maintenance and repair costs for pothole repairs and edge break-up also led to the current timing of the project.

The project includes the following activities and improvements:

  • Existing roadway will be pulverized, re-graded and built-up with an improved granular base to meet the design cross-section
  • Road cross-culverts will be removed and replaced with like for like structures. Private driveway culverts will also be replaced
  • Ditching improvements will be carried out for improved roadside drainage
  • Roadway will be finished with a new double surface treatment (chip seal) and a fog seal

This work is categorized as “Exempt” under the 2024 Municipal Class Environmental Assessment process and is considered a pre-approved construction project under the Ontario Environmental Assessment Act.

Further information on the selected contractor and start dates will be provided on this web page. Notices will also be issued to properties fronting on the project.

The Township of South Frontenac will be reconstructing the 2.0km section of Round Lake Road from Duff Road to Latimer Road during the summer of 2026. Round Lake Road was selected as a priority project for 2026 due to the poor road surface ratings identified within the Township’s 2022 Comprehensive Road Needs Study. The pavement condition ratings for the roadway were 40 (Poor) in 2025. Ongoing increases in unplanned maintenance and repair costs for pothole repairs and edge break-up also led to the current timing of the project.

The project includes the following activities and improvements:

  • Existing roadway will be pulverized, re-graded and built-up with an improved granular base to meet the design cross-section
  • Road cross-culverts will be removed and replaced with like for like structures. Private driveway culverts will also be replaced
  • Ditching improvements will be carried out for improved roadside drainage
  • Roadway will be finished with a new double surface treatment (chip seal) and a fog seal

This work is categorized as “Exempt” under the 2024 Municipal Class Environmental Assessment process and is considered a pre-approved construction project under the Ontario Environmental Assessment Act.

Further information on the selected contractor and start dates will be provided on this web page. Notices will also be issued to properties fronting on the project.

  • June 24, 2026

    UPDATE – June 24, 2026 – The Round Lake Road Reconstruction project from Latimer Road to Duff Road will be starting soon. Township forces will be completing this work. Weather dependent, crews are planning to mobilize to the project to starting July 9, construction activities will continue for approximately 6 - 8 weeks through to the end of August. During construction, lane closures and traffic delays should be expected. Notifications of the project will also be sent to emergency services and school transportation providers.

    For further updates on the project please follow this engagefrontenac project page. Thank you for your cooperation as we work to improve local roads and bridges in South Frontenac.

    UPDATE – June 24, 2026 – The Round Lake Road Reconstruction project from Latimer Road to Duff Road will be starting soon. Township forces will be completing this work. Weather dependent, crews are planning to mobilize to the project to starting July 9, construction activities will continue for approximately 6 - 8 weeks through to the end of August. During construction, lane closures and traffic delays should be expected. Notifications of the project will also be sent to emergency services and school transportation providers.

    For further updates on the project please follow this engagefrontenac project page. Thank you for your cooperation as we work to improve local roads and bridges in South Frontenac.