Why is the road being reconstructed now?

    Bedford Road from approximately 1 km north of Salmon Lake Road to Desert Lake Road has some of the poorest surface condition ratings of all of the hard surfaced roadways in the Township. The road surface is considered to be well beyond the state where it can be reasonably maintained or rehabilitated. Total reconstruction is required.

    When will construction start?

    Construction is expected to start in July 2024 and last until September 2024.

    Who will complete the work?

    Construction activities will be led by Crains’ Construction. Crains’ Construction has successfully completed multiple projects for the Township. Separate notices will be issued by their company for after hours contact information.

    How will this affect traffic in the area?

    A minimum of one lane will be open during active construction except for one planned 24-hour road closure. Notice will be provided to residents and emergency services before the closure, along with an approved signed detour. Traffic delays should be anticipated from time to time for the project's duration. Drivers should drive cautiously and obey traffic signage and personnel at all times.

    Is there anything I need to do to prepare for the construction?

    Landscaping features, flowers, fencing, or other physical objects located in the Township road allowance in front of your property may need to be relocated before construction begins to avoid damage. Landowners will be individually contacted where concerns are found.

    What do I do if I have mobility or accessibility needs or concerns?

    Individuals with mobility or accessibility needs should contact the Township to discuss accommodations needed during construction. The Township will work with landowners to accommodate resident requirements wherever possible.

    How will this impact mail delivery?

    Access to mailboxes may be restricted for a short period of time while the work is being carried out. Mailboxes that need to be removed will be reinstalled at the sole cost of the Township. Residents will be notified prior to mailbox relocation.

    Will my driveway access be impacted by construction?

    Resident access to their properties may be restricted for a short period of time while certain works are being carried out. The Contractor will aim to provide a minimum of 24 hours notice ahead of these planned disruptions.

    Will construction interfere with garbage or recycling collection?

    Residents should continue to place garbage and recycling out for collection at end of their driveway by 7 am on their regular collection day. During construction, the Contractor may move a resident’s garbage and recycling materials to a centralized collection location for safety and convenience. The Contractor will return recycling boxes and garbage cans to each property after collection has been completed. Residents can help by adding their civic address to their blue boxes or garbage cans using a permanent black marker.

    What will the Township do about dust control?

    During construction, the Contractor will be responsible for dust control. Watering trucks and/or dust suppressants will be used to manage dust control.

    Will the fence at the front of the lot be impacted by the construction work?

    If any grading or ditching work has an impact on fencing, the Township will contact individual landowners in advance to discuss the details of any improvements prior to the work.

    What will the hours of work be on the project?

    Work will typically be done Monday to Friday from 7 am to 7 pm in accordance with By-Law 2015-41 - To Prohibit and Regulate Noise Within the Township of South Frontenac.   

    Weekend work may be considered late in the project if weather delays are encountered. If weekend work is deemed necessary, advance notice will be provided to the area so that residents may plan accordingly.

    What do I do if I live on the road and have key events or activities (moving, family gathering, weddings, pool installations, site construction, etc..) planned this summer?

    Residents are encouraged to reach out to the Township in advance to advise of any special events or activities that may be happening at their property this summer. Township crews will do their best to plan or schedule works in a manner that reduces inconveniences where possible.

    Please contact Public Services at 613-376-3027 or email pwsupport@southfrontenac.net.

    Will I be able to park on the road this winter or summer?

    No parking will be allowed on the road for the duration of construction.

    How do I stay informed on this project as it progresses?

    Residents within the work zone on Bedford Road and surrounding areas are encouraged to subscribe or follow this project online to stay up to date on the progress.

    Other options include reaching out by phone to 613-376-3027 or by email to pwsupport@southfrontenac.net with contact information for your property. This will help the Township keep you informed as the project continues. Email addresses can be used to push information updates to residents, however individual addresses will not be shared for any other purpose. Please use the subject line “Bedford Road Reconstruction”.