October 30, 2026

UPDATE – October 30th, 2026

Works completed – weeks of September 17 to October 30

  • Stage 2 concrete removals
  • Stage 2 bridge deck placement
  • Stage 2 approach slab and curb placements
  • Stage 2 expansion joint installation


Works forecasted – weeks of November 2 to November 13

  • Stage 2 bridge deck waterproofing
  • Stage 2 paving
  • Stage 2 guide rail installation
  • Clean up and demobilization from site