August 28, 2026

UPDATE – August 28, 2026

Works completed to date

  • Stage 1 Bridge jacking and bearing replacements
  • Stage 1 Removal and reinstallation of bridge curbs, bridge deck and approach slabs
  • Placement of new Stage 1 expansion joints
  • Patching of abutments and wing walls
  • Stage 1 Railing installation

Works forecasted – weeks of August 31 to September 17 (weather permitting)

  • Stage 1 Installation of bridge deck waterproofing
  • Stage 1 paving
  • Stage 1 Guide rail installation
  • Switch over to stage 2